Building a villa in Bali: the permits, in the order the law sets
Key takeaways
- PP No. 28 Tahun 2025 sets the order: legality, basic requirements, then the license.
- The basic requirements are KKPR, PL, and PBG and SLF. The KKPR comes first.
- Construction starts after the PBG — and the business must hold PL and PBG before building.
- The SLF is a basic requirement of the license, and the villa may operate once licensed: for a villa, an NIB and a standard certificate.
- Protected farmland may not be converted at all. The KKPR tells you which plot is which.
Most of Bali's villa licensing trouble is built in: a building put up before its approval, on a plot whose use does not allow it, with a function on paper that does not match what it does. The permits come in a fixed order, and each one depends on the one before.
Eight steps, in order
| What | Rule | |
|---|---|---|
| 1. Business legality | NIB on OSS, with the KBLI and location | PP 28/2025 Pasal 8, 206-207 |
| 2. Spatial conformity | KKPR: confirmation against the RDTR, or approval | PP 28/2025 Pasal 12, 15-19 |
| 3. Environment | Environmental approval, or the SPPL statement for small activities | PP 28/2025 Pasal 8, 11(3), 12 |
| 4. Building approval | PBG, before construction starts | PP 28/2025 Pasal 11(3); PP 16/2021 Pasal 263 |
| 5. Construction | To the approved plan and function | PP 16/2021 Pasal 11 |
| 6. Certificate of function | SLF, a basic requirement for the license | PP 28/2025 Pasal 12; PP 16/2021 |
| 7. Business license | Standard certificate on OSS; self-assessment and health certificate | PP 28/2025 Pasal 131, 221; Permenpar 6/2025 |
| 8. Operate | Once the license is held | PP 28/2025 Pasal 11(4) |
Each step, and what it decides
The plot: KKPR
Spatial conformity is the first basic requirement: a confirmation where a detailed plan is on OSS, issued or refused automatically; an approval after review where it is not. It states the activity, the building coverage and floor area ratios and the building rules. Zoning and the KKPR.
Protected farmland
Land designated as sustainable food farmland is protected and may not be converted; an individual who converts it faces up to 5 years and IDR 1 billion (UU 41/2009, Pasal 44, 72).
The building approval: PBG
A business that will construct a building must hold the environmental approval and the PBG (PP 28/2025, Pasal 11(3)); construction begins after the PBG (PP 16/2021, Pasal 263). The function written on it — house or business — follows the building through its life. The PBG and its levy.
Planning to build?
Tell us which part of Bali the plot is in. Five questions, and your details are the last step.
The certificate of function: SLF
The SLF certifies the building fit for its function and is one of the basic requirements of the license (PP 28/2025, Pasal 12); it is renewed every 5 years for buildings other than houses. The SLF.
The business license
A villa is medium-low risk: the license is an NIB and a standard certificate, the certificate being the business's own statement, with a self-assessment document and a health certificate under the villa standard. The standard.
Then guests
For low and medium-low risk activities the business may operate once it holds its license (PP 28/2025, Pasal 11(4)).
Design for the function you will use
The function written on the PBG follows the building: it appears on the PBG, the SLF and the building ownership certificate (PP 16/2021, Pasal 11(1)), and changing it later needs an amended PBG (Pasal 11(2)). A villa built as a house and let to guests is the most common mismatch in Bali. The levy reflects the choice: Denpasar's PBG formula weights a business building at 0.7 against 0.15 to 0.17 for a house — roughly four times — and in Badung the levy covers the PBG and the SLF. Building as a house to save on the levy, and letting it anyway, buys a change-of-function application later, with sanctions for the mismatch in between.
Where a step can stall
Where a detailed spatial plan is integrated with OSS, the KKPR is issued or refused automatically; where it is not, the approval route adds registration, review, assessment and a state fee payable within seven days of the payment order (PP 28/2025, Pasal 17-19). Plots outside a detailed plan therefore take the slower path before any building approval can start.
An older villa
An IMB stays valid until it expires; a building with neither IMB nor PBG goes through the SLF route first (PP 16/2021, Pasal 346). The old IMB.
What this page does not cover
- Any regency's spatial plan. Read through the KKPR, not here.
- Construction contracts. Hiring a builder: licenses, the contract and the 10-year liability.
- Environmental approval in detail. SPPL, UKL-UPL and the 2025 wastewater rules; a bore well's license and tax.
Common questions
What permits do I need to build a villa in Bali?
In order: business legality (NIB), spatial conformity (KKPR), the environmental approval or statement, the building approval (PBG) before construction, the certificate of function (SLF), and the business license — for a villa, the NIB plus a standard certificate (PP No. 28 Tahun 2025, Pasal 8, 11, 12, 131).
Can I start building before the PBG?
No. Construction begins after the PBG (PP No. 16 Tahun 2021, Pasal 263), and a business that will construct a building must hold the environmental approval and the PBG (PP 28/2025, Pasal 11(3)).
Can I build on rice-field land?
Not on land designated as protected food farmland (LP2B), which may not be converted; an individual who converts it faces up to 5 years and IDR 1 billion (UU No. 41 Tahun 2009, Pasal 44 and 72). What a plot allows is what the KKPR states.
What does the PBG cost?
It is a regional levy set by each regency. Denpasar's formula weights a business building about four times a house; Badung's levy covers the PBG and the SLF. The PBG page sets out both.
When can the villa take guests?
Once it holds its business license (PP 28/2025, Pasal 11(4)) — after the SLF and the standard certificate.
Sources cited on this page
- PP No. 28 Tahun 2025 — Pasal 8, 11, 12, 15-19, 131
- PP No. 16 Tahun 2021 — PBG and SLF
- PP No. 21 Tahun 2021 — KKPR
- UU No. 41 Tahun 2009 — protected farmland
- Permenpar No. 6 Tahun 2025 — villa standard
Every figure above links to the source it was read from. This page was last changed on 4 October 2026. How we check this.